AT&L Supports Delivery of Major
Logistics Hub for Amazon

Project Details

Date

2021-2026

Client

Goodman

Infrastructure Value

$18M

Service

AT&L provided end-to-end civil engineering services, including civil design, service co-ordination, authority approvals, stakeholder management, project management and construction support to facilitate successful project delivery and Statement of Compliance outcomes.

Project Overview

The Amaroo Business Park project existed as a large-scale industrial estate delivered across approximately 40 hectares through a staged approach. 

  • Stage 1: 13.1ha including a major logistics facility, the Amazon sort centre  
  • Stage 2: ~19ha future development parcel  

The project sat within a complex authority environment: 

  • Hume City Council  
  • Department of Transport and Planning Victoria  
  • Melbourne Water  
  • Yarra Valley Water  

Key infrastructure requirements included: 

  • Council road upgrades and new roundabout  
  • Scheme drainage with wetland and retarding basin  
  • Lead-in services across freeway and rail corridors  
  • Significant bulk earthworks  
  • High-risk service crossings including fibre infrastructure 

AT&L’s Role & Key Infrastructure Features

AT&L led the civil engineering and delivery coordination across the full project lifecycle. 

Scope included: 

  • Civil design – roads, drainage, bulk earthworks (excluding on-lot works)  
  • Service coordination – sewer, water, drainage, electrical, NBN  
  • Authority approvals and stakeholder management  
  • Project management and programme coordination  
  • Construction phase support and delivery interface  
  • Statement of Compliance facilitation  

This ensured all infrastructure elements were aligned across multiple authorities, contractors, and delivery stages. 

Design Innovations That Reduced Disruption

The project required careful planning to avoid delays across approvals, construction, and tenant delivery. 

Key design decisions focused on reducing friction: 

Staged infrastructure delivery to unlock early authority sign-offs for critical services 
Split servicing strategies, including sewer deeds, to fast-track approvals and construction  
Progressing selected works ahead of approvals, with managed risk alignment with the client  
Optimising service corridors across major constraints like freeway and rail crossings  
Adapting designs in real time to manage construction risks such as cable protection, service relocation, and material changes  
Amaroo

Key Outcome & Benefits

Delivered both stages on time and under budget despite complex, high-risk constraints
Aligned infrastructure with Amazon facility and title release, avoiding delays
Secured multi-authority approvals within tight timeframes, reducing programme risk 
Enabled staged delivery without delaying future development 
Reduced cost and rework through coordinated, buildable design 

Client Testimonial

AT&L’s role in the Amaroo project required multiple dynamic approaches to not only Authority specific requirements and constraints, but also to Goodman’s changing requirements to meet an evolving uncertain commercial landscape to meet market demands. In this capacity AT&L worked well to ensure maximum flexibility could be designed and met to meet these ever-changing demands and outcomes. Lot configurations and authority servicing requirements changed multiple times over the journey, AT&L tailored their approach to meet our demands and delivered on their project expectations.

Matthew O’Brien, Project Manager – Infrastructure, Goodman

This project demonstrates how strong coordination, proactive design, and staged delivery can unlock complex industrial developments without slowing down commercial outcomes. 